Construction site safety plans
Although required by some states for general construction, a written comprehensive Safety and Health Plan is not required by the Occupational Health and Safety Administration for construction projects involving installation or building of concrete structures. Nevertheless, significant advantages of a well written plan include (1) administrative organization in complying with project requirements, which typically impresses OSHA inspectors, and (2) assurance of adequate administrative preparation for the project. When these elements are contained in a single document, an inspector can conveniently reference the Site Safety Plan to verify the presence and implementation of OSHA requirements — an immensely helpful measure in preventing citations.
Few construction companies initiate projects without written safety plans. Correctly performed, a safety plan would be incorporated during the preparatory phase of a construction project, identifying all steps of the job and necessary measures to mitigate hazards — like a comprehensive Job Safety Analysis.
Safety plans vary in content, since no single standardized document for the development of job-site safety plans is available. Although plans vary among employers, the following elements are recommended:
First aid and medical care availability
OSHA requires that the employer provide first aid and medical care for potentially injured workers. In the interest of good incident management, a first-aid kit should be accessible and at least two on-site persons certified in First Aid and CPR. If the site is in a 911-call system, this information should be posted. If the site is outside a 911 system, numbers for the local fire department, ambulance service, and police should be provided.
To effectively manage incidents and provide better care for routine, nontraumatic injury, the name and address of an industrial clinic is preferable to an emergency room listing. Trauma is the specialty of emergency rooms, while a walk-in industrial clinic is set up to handle routine industrial injuries, such as cuts, sore backs, muscles strains, drug testing, and bruises. Additionally, such clinics will tend to work with the employer to minimize an incident's recordability, if incident factors related to mandatory OSHA reports can be minimized.
Posters
Local emergency phone numbers should be displayed on a poster, usually in the construction trailer. Most importantly, the OSHA poster needs to be placed where all personnel can see it — typically, a bulletin board or time-clock poster board that may also include Family Leave, Wage and Hour, Child Labor, Anti-discrimination, state OSHA notices, and company announcements. The OSHA poster is available online at osha.gov.
Hazard identification, mitigation, and training
OSHA requires that employees and their supervisors be trained in specific hazards and control measures associated with their assigned tasks. Accordingly, Job Safety Analyses should be completed, providing the following three components:
- Identification of procedural steps of a job task
- Identification of the hazards of each step
- Identification of steps to reduce the hazard
Such information is provided using a form similar to that shown on page 44.
Once JSAs have been developed, the supervisor can review the job steps of daily activities, identify the hazards of each step, and discuss preventive measures. These JSAs are typically held in a binder with employees' attendance-sheet signatures attached to the document. The attendance sheet verifies that the training was completed. While traditionalists contend that training is not completed until an employee is tested and demonstrates his or her comprehension, most construction sites accept daily review and signature sheets as adequate.
For ease of administration, standardized JSAs can be developed for similar tasks and modified on-site when local conditions dictate specific measures. Individual JSAs, for example, could be developed for jobs such as concrete forming, mesh placement, rebar placement, laying block, excavation and trench preparation for pipe installation, panel erection, and beam placement.
Company safety policies, procedures and hazard-control references
The multitude of safety policies and programs required by various government regulations and industry standards can be included in the safety plan; more frequently, however, they are simply referenced as appropriate. These policies and programs are necessary (1) to verify that the hazards associated with the work at hand have been mitigated by company safety procedures and policies, and (2) to maintain compliance with regulatory requirements for a written program.
Training documentation
Recommended are documentation of Competent Person(s) certification or other training verification, plus worker equipment-operation certifications. Competent Persons are designated by the company and should be named in the plan.
Training is required for mobile equipment, cranes and hoists, and hydraulic jacking equipment. Additional documentation would record all standard OSHA training required for a jobsite, e.g., HazCom and PPE.
Most companies do not have the administrative staff to create detailed, project-specific site safety plans without the aid of a standardized form. Typically, a template is developed that includes redundant company policy and procedural information with a fill-in-the-blank format for remaining site-specific variables. Small jobs with only a few individuals may entail reduced administrative plan prep time, as a one-page form need only be inserted in the front of a standardized site-safety plan completed by the supervisor. Such documentation usually includes project name, date, supervisor name (also the Competent Person), and a pocket card that functions as a JSA requiring identification of each job-task step, anticipated hazard(s), and preventive measure(s). Intended for completion before every task, the card is typically filled out prior to every shift, reviewed with other workers, and signed by the employees present.
Regardless of size, any construction job should include the preparation of some form of site safety plan. While this industry best practice is not yet a regulation, it exemplifies an honest effort to exceed OSHA requirements and to minimize incidents on the job.
Large construction project site safety plan outline
| Tab Title | Section Contents |
|---|---|
| Title Page | |
| Plan | Objective and Project Description Definitions |
| Administration | Organization Orientation Training requirements and documentation Safety Meeting Schedule Competent Persons Identified Audits/Inspection schedules Accident Management Available Safety Assistance Interpretative Resolution Contact Dispute Resolution Contacts Forms (safety meeting, inspections, emergency contact poster, OSHA poster) |
| Project Safety Guidelines | Medical/First Aid Availability Fire Protection Housekeeping Hot Work and Flame Permit Confined Space Entry Personal Protective Equipment Appropriate Attire Signs, Signals and Barricades Elevated Work Areas Scaffolding Lockout/tagout Crane and Motorized Equipment Operation Crane and Motorized Equipment Inspections Crane Suspended Personnel Baskets Drug and alcohol testing requirements, if any Tool and Equipment Inspection Ground Fault Protection Physical Health Hazards Hazardous Materials Management Spill Prevention Demolition Excavations Special Project Precautions Site Restrictions |
| Responsibility | Project Manager Supervisors Safety Coordinator Workers |
| Emergency (in red or bold letters) | Phone Numbers Emergency Procedures |
| JSA | Job Safety Analysis |
Small construction project site safety plan outline
| Tab Title | Section Contents |
|---|---|
| Title Page | |
| Plan | Identify where company policies and procedures can be located Identify the company safety contact Identify the site safety contact (usually the supervisor) |
| Administration | Safety meeting schedule Competent persons identified Audits and inspections schedules Forms (safety meeting, inspections, emergency contact poster, OSHA poster) |
| Project Safety Guidelines | Medical/first aid availability Project job safety analyses Special project precautions Site restrictions |
| Emergency (in red or bold letters) | Phone numbers Incident and emergency management |
Construction safety plans
A construction safety plan can assist principal contractors to manage their workplace health and safety obligations.
A principal contractor must prepare a construction safety plan before construction work starts.
The plan must state:
-
workplace address
-
name and address of the principal contractor
-
principal contractor's ABN
-
whether there is a WHS committee
-
whether there is a WHS Officer appointed
-
expected start date
-
estimated duration of the work
-
type of construction
-
site rules
-
the risks the principal contractor is obliged to manage
-
proposed control measures for the risks
-
how the controls will be implemented
-
arrangements for monitoring and reviewing controls
The plan must be written so it is easy to understand, signed and dated by the principal contractor. It must be available for the length of the project.
The principal contractor must sign and date work method statements that have been received and keep them with the plan, as well as monitor their implementation.
The principal contractor cannot allow work to start unless:
-
the plan has been discussed with or a copy given to all relevant people
-
the plan is available or readily available for inspection.
The plan must be amended if there are changes in how risks will be managed. The principal contractor must inform any affected person of the change.
Work method statements
Work method statements can assist relevant people to consider how certain activities will be carried out safely.
A relevant person doing construction work needs to prepare a work method statement for high-risk activities including:
-
where a person is –
-
to enter a trench more than 1.5 metres deep
-
using explosives
-
using a confined space
-
using a hazardous substance
-
-
if a person could fall–
-
at least 3 metres for housing construction work, or
-
at least 2 metres for other construction work
-
-
working on a roof with a pitch greater than 26°
-
where the principal contractor concludes an activity could result in death or bodily harm
-
demolition work or asbestos removal work (prescribed activities).
A work method statement is also required for high-risk activities which include:
-
tilt-up and precast construction work
-
structural alterations that require temporary support to prevent collapse
-
moving powered mobile plant at the workplace
-
working on a telecommunications tower
-
working in, over or adjacent to water where there is a risk of drowning
-
working on, or adjacent to, a road or railway
-
working on or near a pressurised gas distribution mains and consumer piping
-
working on or near a chemical, fuel or refrigerant line
-
work near an exposed energised electrical installation
-
work in an area that may have a contaminated or flammable atmosphere
-
work in an area where there are artificial extremes of temperature.
The work method statement must take into account the principal contractor’s construction safety plan and also state:
-
the high-risk construction activity
-
the person’s ABN
-
the control measures to be used
-
the way the activity will be performed
-
how the control measures will be monitored and reviewed
-
any relevant prescribed occupations.
For demolition work and asbestos removal work (prescribed activities) the work method statement must also state:
-
the relevant certificate number
-
the arrangements for appropriate training and supervision
-
take account of AS 2601 Demolition work (non-Queensland Government link) for demolition work.
Work method statements must be easy to understand, signed and dated.
The work method statement must be amended if there is a change in the activity and a copy must be given to the principal contractor. All people affected by changes must be advised of amendments to the work method statement.
The work method statement must be readily available for inspection. It must also be reviewed each year and amended if necessary.
reference: Queensland government-Australia

While there are many things important to concrete construction, such as quality work and making a profit, safety must always be the No. 1 priority. For that reason, we are starting with safety to emphasize its importance as critical to a successful project.
Most accidents are preventable. Accidents are often due to carelessness and not thinking through what you are doing. You MUST plan for safety. The following list of things to watch out for on a concrete construction jobsite is not intended to be comprehensive. It does, however, serve to alert you to some of the more common safety in concrete
ادامه مطلب

معمولا وقتی صحبت از ظرفیت یک جرثقیل میشود منظور حداکثر باری است که جرثقیل می تواند با شرایط زیر حمل کند.
۱- فاصله بار تا مرکز بوم حداقل باشد (فاصله تا Center pin )
۲- بازوهای جرثقیل تا انتها باز شده باشند (outriggers)
بدیهی است که با فاصله گرفتن بار از مرکز ظرفیت بارگیری کاهش میابد
برای درک بهتر می توانید فایل زیر را که به زبان انگلیسی می باشد برای جرثقیل Terex RT345 مشاهده کنید.

در صورت تمایل میتوانید هر دو فایل را از اینجا دانلود نمائید

در مواردی که حادثه ای در کارگاه اتفاق می افتد از سوی دپارتمان ایمنی گزارشی مشروح از ما وقع تهیه شده و ارائه می گردد. این گزارشها بیانگر علل حادثه و روشهای جلوگیری از آن در آینده می باشد معمولا با ذکر دقیق و مشروح روند ایجاد حادثه بررسی میگردد
در زیر می توانید یک نمونه گزارش را که به زبان انگلیسی می باشد مشاهده نمائید

در صورت تمایل عکسها را از اینجا دانلود نمائید


در صورتی که قادر به دیدن تصاویر نیستید لینک های زیر را باز نمائید
در صورت تمایل می توانید عکسها را از اینجا دانلود نمائید


در صورت تمایل می توانید 6 عکس مربوطه را از اینجا دانلود نمائید
در صورت تمایل می توانید فیلم را از اینجا دانلود نمائید
در فایل زیر می توانید ابعاد انفجار یک خط لوله گاز همراه با بررسی دقیق عوامل آن و میزان خسارات وارده را مطالعه نمائید
دانلود فایل فایل pdf با حجم ۲ مگابایت

دانلود PFD حجم فایل 4.73mb

بندهایی از مبحث 12 مقررات ملی ساختمان
12-1-5-5 در کارگاه ساختمانی بناهای با زیربنای بیش از 3000 مترمربع و یا با ارتفاع بیش از 18 متر از روی پی و یا داشتن حداقل 25 نفر کارگر و همچنین در گودبرداری بیش از 3 متر از کف گذر، مجری موظف به تعیین مسئول ایمنی و معرفی وی به کارکنان و مهندس ناظر می باشد. تعیین و حضــور مسئول ایمنی در کارگاه رافع مسئولیتـهای قانونی مجری و مسئولین مربوطه نمی باشد.
12-1-5-7 کارفرما نباید به هیچ کارگری اجازه دهد که خارج از ساعت عادی کار، به تنهایی مشغول به کار باشد. در صورت انجام کار در ساعت غیر عادی، باید روشنایی کافی و امکان برقراری ارتباط و نیز تمام خدمات مورد نیازکارگران فراهم شود.
12-2-4-9 وسائل و تجهیزات اطفاء حریق الف: سطلهای آب و ماسه و کپسولهای خاموش کننده (متناسب با نوع حریق) و سایر وسایل قابل حمل که به منظور اطفاء حریق به کار می روند، باید در قسمتهای مختلف کارگاه ساختمانی به نحوی که همواره در معرض دید و دسترس باشند، نصب و آماده استفاده گردند.
12-2-5-3 درکارگاه ساختمانی بناهای با زیر بنای بیش از 3000 مترمربع باید وسایل ارتباطی برای تماس فوری با مراکز اورژانس وآتش نشانی فراهم گردد.
12-3-1-2 در عملیات ساختمانی، به کارگرانی که به طور مستمر با گچ، سیمان یا سایر مواد آلوده کننده تماس مستقیم دارند، باید یک بار برای هر شیفت کاری شیر داده شود.
12-3-3-1 در هر کارگاه ساختمانی باید به ازای هر 25 نفر کارگر، حداقل یک توالت و دستشویی بهداشتی و محصور، با آب و وسایل کافی شستشو ساخته و آماده شود. در هر کارگاه ساختمانی وجود حداقل یک توالت و دستشویی الزامی است.
* جابجایی کارگران با جرثقیل باید توسط سبد های ایمن صورت گیرد
* ارتفاع دیواره این سبدها نباید از 120 سانتی متر کمتر باشد
*سبدها باید با دو کابل مجزا به قلاب جرثقیل متصل شوند یعنی در چهار گوشه سبد باید جای قلاب وجود داشته باشد
*دو کابل باید به صورت ضربدری بسته شوند یعنی یک کابل از دو قلاب به صورت قطری باید عبور کند
*سبدها حتی الامکان دارای جعبه ای جهت قرار دادن ابزارآلات داشته باشند
*کف سبدها تا ارتفاع 40 سانتی متر دور تا دور از ورق پوشیده شده باشد تا از سقوط ابزارآلات جلوگیری شود
*در صورتی که سبد دارای در می باشد باید این در دارای ضامن یا قفل ایمنی باشد
*کارگران هنگام سوار شدن بر سبد موظف به استفاده از کمربند ایمنی می باشند
*قبل از استفاده از سبد افسر ایمنی باید آنرا همراه با کابلها بازرسی نماید و بر چسب اطمینان یا کدرنگ ایمنی بر روی آن بچسباند.

جهت دانلود عکسها اینجا کلیک کنید
من نمیدونم ساختمان به این بزرگی چرا افسر ایمنی نداره و چرا کارگران در این زمینه آموزشی ندیده اند. چنین حادثه ای اگر در کشوری مانند سنگاپور یا ژاپن اتفاق بیفتد حتی اگر کسی آسیب نبیند چنان طوفانی از بازخواست راه می افتد که هیچ مسئولی را مفری نیست. استفاده از جرثقیل جهت جابجایی کارگران شرایط خاصی دارد که بزودی در وبلاگ مطرح خواهم کرد





از دیگر مواردی که در این مراسم صحبت به میان آورده میشود اتفاقات و حوادثی است که در آن کارگاه و یا کارگاههای دیگر اتفاق افتاده است. ضمن تشریح حادثه راهکارهای مناسب جهت جلوگیری از تکرار حادثه نیز بررسی میشود.

یکی از وظایف افسران ایمنی در کارگاه سرکشی به استراحتگاه کارگران و بررسی شرایط ایمنی محل ذکر شده می باشد.




شرکتهای معتبر ساخت و ساز در دنیا دارای خط مشی در زمینه ایمنی می باشند بدین معنا که علاوه بر رعایت قوانین ایمنی کشور ٬قوانینی خود شرکتها جهت تضمین ایمنی وضع می کنند. به این قوانین سیاستهای ایمنی شرکت و یا خط مشی ایمنی شرکت گفته می شود.شما نیز اگر صاحب شرکتی می باشید و به مبحث ایمنی نیز اهمیت می دهید توصیه می کنم چنین برنامه ای در شرکت خود ایجاد و پیمانکاران خود را ملزم به رعایت آن نمائید.
جهت آشنایی شما با این گونه سیاستها یک نمونه از آنرا می توانید از لینک زیر دانلود نمائید
دانلود فایل حجم فایل ۱۴۰ کیلوبایت
روشهای جلوگیری از سقوط و
شیوه و شرایط استفاده از body harness
اگر قادر به دیدن فیلمها نیستید آنها را از لینکهای زیر دانلود نمائید
فیلمی آموزشی در ارتباط با لوازم محافظتی شخصی یا personal protective equipment
اگر قادر به دیدن فیلم نیستید آنرا از لینک زیر دانلود نمائید
فیلم آموزشی کوتاه درباره وظایف مهندس ناظر یا افسر ایمنی جهت حفظ ایمنی کارگاه
اگر قادر به دیدن فیلم نیستید می توانید آنرا از لینک زیر دانلود نمائید
دانلود فیلم آموزشی ایمنی در کارگاه
۱- جرثقیل و بالابر
۲-درهای خروجی
۳-بازشوها
۴-ppe
۵- راهروها
http://www.4shared.com/file/59864975/5009709f/cranes_n_hoists.html
http://www.4shared.com/file/59864976/c9002125/exit_doors.html
http://www.4shared.com/file/59864978/2eb80c22/floor_wall_opens.html
http://www.4shared.com/file/59864979/59bf3cb4/personal_protect_equip.html
http://www.4shared.com/file/59864973/b96ad5aa/walkways.html
تعداد ۱۱ عکس از علائم و هشدارهای ایمنی را می توانید از لینک انتهای پست دانلود نمائید.
قابل توجه اعضا وبلاگ: در صورتی که نیازمند تابلو با نوشته خاصی هستید این کار به صورت رایگان برای شما انجام خواهد شد کافیست تا در قسمت تماس با مدیر متن مورد نیاز را ثبت و شناسه وبلاگ خود را نیز بگذارید تا تابلو از طریق ایمیل برای شما ارسال گردد

دانلود هشدارهای ایمنی حجم فایل ۱.۳۵ مگابایت
۱- موضوع
۲-موقعیت مکانی
۳-نام شخص مسئول یا مهندس بخش مربوطه
۴-شماره عکس مربوطه
۵-توضیحات اضافی

در ارتباط با اکسیژن کافی نیز می توانید از Gas detector استفاده نمایید. معمولا این دستگاه ها قابلیت تشخیص اکسیژن و همچنین گازهای اشتعالزا را دارا می باشند. در صورت وجود گاز اشتعالزا بیش از حد مجاز دستگاه اعلام خطر میکند.


در تصویر زیر اگر به قلاب جرثقیل توجه کنید می توانید برچسب زرد رنگ را ببینید



دانلود فایل pdf باحجم ۴.۸ مگابایت

دانلود فایل حجم ۵۰۰ کیلوبایت

دانلود فایل حجم ۱۳۰ کیلوبایت

دانلود فایل حجم ۳۵ کیلوبایت
۱-زمان انجام عملیات باید به اطلاع همه افرادی که در کارگاه رفت و آمد دارند برسد(معمولا در بخش اداری تابلوهایی وجود دارد که بر روی این تابلوها اطلاعات مربوطه درج می گردد)
۲-در کارگاه محیطی که در آن صدا تولید میشود باید از دیگر قسمتها جدا سازی شود (معمولا با نوارهای هشدار )
۳-علائم و تابلوهای ایمنی در محل نصب گردد
۴-افرادی که در محل رفت و آمد می کنند باید از گوشیهای مخصوص صدا گیر استفاده کنند
۵-بر روی کاغذ در محیطهای مربوطه باید ساعات و روزهای انجام عملیات درج گردد.
۱-در قسمت فوقانی محل(بالای سر) نباید هیچگونه فعالیت کاری وجود داشته باشد
۲-این محدوده باید با پانل یا داربست از اطراف جدا گردد
۳- علائم هشدار دهنده باید در محل نصب شده باشد
۴-تابلوی محل سیگار کشیدن باید در محل نصب شده باشد.
۵-در صورت نزدیکی به دیگر قسمت های کارگاه باید کپسول آتش نشانی در محل قرار داده شود
۶-سینی مخصوص خاموش کردن سیگار باید در محل تعبیه گردد(Ash tray)
۷-سطل پر از ماسه باید در محل قرار داده شود


به خاطر داشته باشید که جوشکاری یا هوابرش بر روی مواد قابل احتراق من جمله قالب چوبی ٬ رنگ تازه و ... مجاز نمی باشد جرقه های حاصله از جوشکاری و ... بسیار خطرناک می باشد. برای جلوگیری از خطر باید از پارچه های ضد حریق استفاده نمود (fire blankets) کافیست تا این پارچه در محدوده زیر دست جوشکاری یا هوابرش پهن شود. به عکسهای زیر توجه کنید:
بحث امروز در مورد تابلوهای هشدار دهنده می باشد. هر مهندس عمران موظف است تا به محض ورود به کارگاه از ایمنی کارگاه اطمینان حاصل کند یکی از موارد ایمنی تابلوها هستند که باید بدون خدشه و خوانا متناسب با وضعیت محیط و خطرات موجود در آن نصب شوند اگر در کارگاه کارگرانی از ملیت های متفاوت کار می کنند باید علائم هشدار دهنده به زبانهای دیگر نیز ترجمه شده و در زیر هر تابلو درج گردد.



نکته دیگر آنکه در جلوی در ورودی کارگاه باید شرایط عمومی ایمنی روی یک تابلو ذکر گردد (عکس آخر-سمت چپ) همچنین نگهبانی موظف است تا از ورود افرادی که وسائل ایمنی (PPE) همراه ندارند به کارگاه جلوگیری نماید.
در مورد داربست نیز پس از اتمام کار باید توسط افسر ایمنی یا شخص ذیصلاح بازدید و برگه مخصوص بازدید امضا گردد( عکس ردیف دو -سمت راست)
(وسائل ایمنی:PPE یا personal protective equipment)
شامل تجهیزات زیر می باشد:
۱-کمر بند ایمنی(Safety belt)
۲-کفش ایمنی(Safety shoe)
۳-عینک ایمنی(Safety glasses)
۴-کلاه ایمنی(Helmet)
۵-دستکش(Glove)
۶-ماسک تنفس(Mask)
۷-Body harness(در صورت کار بر روی اسکلت فلزی)


Body harness کمربند ایمنی:Safety belt