Subject: Excavation without prior notice
Dear Sirs
Refer to the above captioned, we would like to highlight our deep concerns on some items as below:
1- YOUR COMPANY did not follow OUR COMPANY’s comment to make hard barricade around FGH#31, which was agreed on M.O.M (08/Jul/2008). Please find the attached photograph on 14/July/2008.(Attachment#1)
2- YOUR COMPANY did not follow the relevant schedule commented by OUR COMPANY on M.O.M (10/July/2008).
In that comment, OUR COMPANY instruct YOUR COMPANY to do excavation near Building1 during equipment non-operation period. (Attachment#2)
3- YOUR COMPANY excavated south side of Building1 by excavator on 14/July/2008 with out any prior notice to OUR COMPANY, as you were aware equipment were already in operation.
4- In case the excavator hits the pipes at building1, the worse case will be explosion, equipments will damage and surrounding workers will be in danger.
5- We already coordinate work sequence of operating area with Mechanical, Electrical and commissioning. Please follow up M.O.M, our instructions and permit to work system; otherwise it will affect safety and our plant schedule.
Sincerely yours
Mr.
Site Manager
نمونه NCN
Location: Building no.1
Subject: Paving slope
As per attached photographs the slope for the concrete pavement is not acceptable (our company) request (your company) to start repairing the pavement in the above mentioned area, moreover your company have to improve the paving method to avoid such matters happening in the future
your thoughtful understanding is appreciated